Friday, February 20, 2009

Swinyard T.I. 2/16/09 thru 2/20/09

Job Log:
The underground plumbing has been backfilled, compacted and has been filled in with concrete. The new exterior door has been cut out and temporary framing is in place until we get the door and frame. HVAC contractor has delivered materials and is prepared to begin installation on Monday 2/23/09.

Thursday, February 19, 2009

Swinyard T.I. 2/9/09 thru 2/13/09

Job Log-

Summary of work complete: The existing concrete floor has been saw cut and removed to allow for the new underground plumbing. The plumbing has been completed, inspected, and approved by the city inspector. Back-fill and compaction will be completed the week of 2/16/09.